FAQ - History
Previous section: BasicsPrevious section
Basics
HISTORYNext section
Current System
Next section: Current System


  1. What did Montrealers use to get around before the metro?
  2. When did they first get the idea for a metro?
  3. When was the metro founded?
  4. How many stations did it comprise at first?
  5. How long did it take to build?
  6. How much did it cost to build?
  7. Who collaborated in the construction?
  8. Why is there no Line 3?
  9. When were the rest of the lines built?


  1. HOW DID MONTREALERS GET AROUND BEFORE THE METRO?

    The first horse-drawn tramway (Montreal City Passenger Railway Company) was installed in 1861, and the system was retired in 1894. The first electric tramway was opened in 1892. The first bus began service in 1919, but it wasn't until 1925 that the system really became widely used in Montreal.

    As for trolleybuses, Montreal was the first Canadian city to install such a system, on 29 March 1937. They continued to operate until 2:28 a.m., 28 June 1966, just before the metro was opened.

    TOP OF THIS PAGE | FAQ CONTENTS

  2. WHEN DID THEY FIRST GET THE IDEA FOR A METRO?

    On May 15, 1902, a federal act incorporated the Montreal Subway Company to "open up, build, and operate a subway or subways" in Montreal. The first well-documented proposal for such a railway dates to 1910. For more detailed information please see the History and Articles section.

    TOP OF THIS PAGE | FAQ CONTENTS

  3. WHEN WAS THE METRO FOUNDED?

    The metro was officially opened on October 14, 1966.

    TOP OF THIS PAGE | FAQ CONTENTS

  4. HOW MANY STATIONS DID IT COMPRISE AT FIRST?

    The initial network included the 10 stations on the green line between Atwater and Frontenac, the 15 stations on the orange line between Bonaventure and Henri-Bourassa, and the three stations of the yellow line, for a total of 26 stations (including the transfer station Berri-UQAM, then called Berri-de-Montigny). All but six of those stations were opened immediately. The stations Frontenac, Beaudry, Square-Victoria, and Bonaventure were opened over the course of the next few months, and the yellow line was opened to the public on 1 April 1967.

    TOP OF THIS PAGE | FAQ CONTENTS

  5. HOW LONG DID IT TAKE TO BUILD?

    Earth was broken on 23 May 1962. From that date it took 4½ years for the majority of the initial system to be opened to the public and 5 years for the whole of the initial section to be opened. The most recent section, the section between Henri-Bourassa and Montmorency in Laval, was opened on 28 April 2007; the last extension before that was in 1988.

    TOP OF THIS PAGE | FAQ CONTENTS

  6. HOW MUCH DID IT COST TO BUILD?

    The construction of the initial section cost $213,7 million in 1960's dollars, which was considered a bargain.

    TOP OF THIS PAGE | FAQ CONTENTS

  7. WHO COLLABORATED ON THE PROJECT?

    Many hands collaborated on the metro project. It was inaugurated during the mayoralty of Jean Drapeau. The engineer Lucien L'Allier oversaw the project as president of the Commission de transport de Montréal, later the Commission de transport de la communauté urbaine de Montréal. Engineers from the Parisian metro, similar in design and technology to Montreal's, consulted with Canadian engineers on the plans. Some 5000 men and women worked on the construction of the system.

    TOP OF THIS PAGE | FAQ CONTENTS

  8. WHY IS THERE NO LINE THREE?

    The lines are numbered 1 (green), 2 (orange), 4 (yellow) and 5 (blue). Some original plans called for the installation of an an above-ground line with 15 stations ending at Cartierville. It was to use the CN tracks under Mount Royal. This plan was cancelled due to three factors: the fact that the trains would have to use steel wheels rather than the tires used in the rest of the system; the difficulty of the negotiations with the municipalities through whose territories the line would pass; and the announcement of Montreal's hosting of Expo 67, which spurred the construction of the yellow line instead. The CN tunnel and tracks are now used by the Deux-Montagnes commuter train line, however.

    TOP OF THIS PAGE | FAQ CONTENTS

  9. WHEN WERE THE REST OF THE LINES BUILT?

    The timeline was as follows:

    • 6 June 1976: Green line, Préfontaine - Honoré-Beaugrand.
    • 3 September 1978: Green line, Lionel-Groulx - Angrignon.
    • 28 April 1980: Orange line, Lucien-L'Allier - Place-Saint-Henri.
    • 7 October 1981: Orange line, Vendôme - Snowdon.
    • 4 January 1982: Orange line, Côte-Sainte-Catherine.
    • 29 June 1982: Orange line, Plamondon.
    • 9 Jan 1984: Orange line, Namur - Du Collège.
    • 16 June 1986: Blue line, De Castelnau - Saint-Michel.
    • 3 November 1986: Orange line, Côte-Vertu.
    • 15 June 1987: Blue line, Parc.
    • 4 January 1988: Blue line, Acadie - Snowdon.
    • 28 April 2007: Orange line, Cartier - Montmorency.

    TOP OF THIS PAGE | FAQ CONTENTS


Previous section: BasicsPrevious section
Basics
Next section
Current System
Next section: Current System